Building Another Cabin: Doing the Paperwork First This Time

What I have learnt about approvals before starting a second small cabin in Queensland: the 10 square metre shed exemption, building and planning approval, secondary dwellings and owner-builder permits.

In Considering Another Cabin I said that next time I would do the drawings, get the engineering, get the planning approval and sort out the owner-builder side before I picked up a saw. This post is me doing that homework, so I don’t have to do it twice, and so anyone else on the Sunshine Coast thinking along the same lines has a starting point.

None of this is legal advice. It is what the council and the Queensland Building and Construction Commission (QBCC) say on their own websites, read by someone who would rather be building. Rules change, so check the sources at the bottom before you spend any money.

Two different approvals, not one

The first thing that tripped me up is that “approval” means two separate things in Queensland.

Building approval is about whether the structure is safe and meets the Building Code of Australia: footings, framing, tie-downs, fire safety, roof water. You get this from a private building certifier, not from the council.

Planning approval is about whether that kind of building is allowed in that spot on your block: how big, how high, how far from the boundary and the road. On the Sunshine Coast that is the Sunshine Coast Planning Scheme 2014, and for most of us on a house block the part that matters is the Dwelling House Code.

You can need one, both or (in a few narrow cases) neither. A certifier can tell you which, and it is worth paying for that conversation early.

The 10 square metre shed exemption

There is a well-known shortcut, and it is real, but it is narrower than people think.

Sunshine Coast Council says a shed (a Class 10a non-habitable building) can go up without building approval if it meets every one of these:

  • no more than 10 m² in area
  • no side longer than 5 m
  • no more than 2.4 m high, with a mean height no more than 2.1 m
  • still complies with the Building Code (structure, fire safety, roof water drainage)
  • meets the minimum boundary setbacks
  • is not in a registered easement
  • does not load a retaining wall, a council stormwater line or a Unitywater sewer

Miss any one and you need a certifier.

The catch for cabin builders is the word non-habitable. A Class 10a building is a shed, garage or carport. The council’s own building page says converting a shed or storage space into a habitable area like a bedroom needs a development building work permit. So a 10 m² shed is fine as storage or a workshop. Once it becomes somewhere a person sleeps, works or spends their day (a bedroom, studio or home office), it is likely to be treated as habitable, and the exemption is gone. Ask a certifier.

Planning limits for sheds on a house block

Even an exempt shed has to satisfy the planning scheme. In a residential zone on the Sunshine Coast, the council’s shed page says a shed must:

  • be set back at least 6 m from any road frontage
  • not exceed 3.6 m in height
  • have a total floor area no more than 56 m²

Rural and rural residential zones have their own setbacks, so check the Dwelling House Code for your zone.

If someone will live or sleep in it

A cabin someone sleeps in is usually a secondary dwelling (Class 1a), not a shed. On the Sunshine Coast the Dwelling House Code sets its own limits for secondary dwellings, and it needs building approval and must meet the energy-efficiency rules. This is the conversation to have with the certifier first.

Owner-builder: the $11,000 line

If you want to build it yourself, the QBCC’s threshold is the number to know. You need an Owner-builder permit for residential building work valued at more than $11,000, and it should be approved before you start (QBCC can approve work after the fact, but you may be fined).

The part I would have got wrong is how the value is worked out. The QBCC says you add up materials and labour at trade price, including GST, even if you are doing the work yourself for nothing, getting mates’ rates, or using second-hand and salvaged materials. Free timber still counts at retail. My structural insulated roof panels alone came to $904 back in 2020 (see Small Cabin Roofing), and once you price your own labour at what a builder would charge, a modest cabin goes past $11,000 quickly.

Other things the QBCC lists that are worth knowing before you apply:

  • Most people need to complete an owner-builder course first.
  • You can normally get one permit every six years (exemptions are possible).
  • A notice goes on the property title, and if you sell within six years of completion you must tell the buyer in writing.
  • Owner-builders cannot claim on the Queensland Home Warranty Scheme.
  • You still cannot do licensed occupational work such as plumbing, drainage or gas fitting yourself, or remove more than 10 m² of asbestos. (Electrical work in Queensland needs a licensed electrician too.)
  • Owner-builders cannot build multiple dwellings, and the QBCC specifically lists attached granny flats among those. Check with your certifier how a detached cabin on your block will be classed.

What I would do differently, in order

Looking back at the first build, this is the order I would follow now:

  1. Decide what the building is for. Studio, workshop, guest room, someone’s home. That single answer sets the building class, and the class sets almost everything else.
  2. Talk to a certifier before drawing anything. Ask what approvals apply, what drawings they need, and what engineering they expect.
  3. Get the engineering. Footings, bracing and tie-downs for my site’s wind rating. I worked through framework, bracing and the base the first time by reading and asking. An engineer’s sheet would have saved some second-guessing.
  4. Check the planning scheme for setbacks and height on my block.
  5. Cost it honestly at trade prices to see which side of $11,000 it lands.
  6. Do the owner-builder course and apply for the permit if needed.
  7. Then build. Tin roof this time (I like hearing the rain), a simple stable door, plenty of wall, a few strategic windows and a porthole or two.

It is less romantic than a lockdown build. It is also the difference between a cabin you enjoy and one you worry about every time you think of selling.

Footnote: If you have been through this recently on the Sunshine Coast, I would like to hear how long the certifier took and what it cost. Real numbers from real people are worth more than anything I can find online.